| Design Completed : |
February, 2005 |
| Owner
: |
Faculty of Medicine Siriraj Hospital, Mahidol University |
| Structural
Engineer : |
CASE
Co.,Ltd |
| Architect
: |
International Project Administration (INTERPAC) Co.,Ltd |
| Structure
: |
Two similar shape high-rise buildings, each with 22 storeys (75 m.
height) and approximated working area 48,660 sq.m., are designed
for two main purposes -- car parking area in the lower part and
residential area for the upper part. Each building has total 388 rooms
that can serve up to 1,300 students and its full parking capacity is
around 765 cars.
The structural system of the building is reinforced concrete frame and
shear wall with post-tensioned flat slab. The precast external walls are
designed to save the construction time and improve quality of works.
|
|
|
|
|
| Design Completed : |
June, 2004 |
| Owner
: |
Vichaiyut Hospital Co.,Ltd. |
| Structural
Engineer : |
CASE
Co.,Ltd |
| Architect
: |
IT Co.,LTd |
| Structure
: |
A high rise building . There are 24 storeys with a helipad on its top and
a basement floor. The building composes of three main parts. The lower
part of the building is a car park. The middle part is for OPD and the
upper part is for internal patients. Total working area is approximately
50,000 sq.m. The structural system for the lower part is reinforced
concrete flat slab.
The system for middle and upper parts is reinforced concrete beam and
slab system. Since this building will be used as a hospital, its structural
systems are carefully design to withstand natural disaster such as strong
wind and earthquake. |
|
|
|
|
| Location
: |
Paholyothin
Road, Bangkok |
| Owner
: |
Mr.Krisda
Thitipunya |
| Structural
Engineer : |
CASE
Co.,Ltd |
| Architect
: |
CASA
Co.,Ltd |
| Site
Area : |
1
Rai |
| Construction
Area : |
6,938
Sq.m. |
| Project
Cost : |
60
M.Baht |
| DesignCompleted
: |
April,
1994 |
| Structure
: |
Multi
purposes building, 7 stories
height, is designed to
serve 3 main functions,
i.e.automobile showroom,
service center and office
space. |
|
|
| |
|
|
| Location
: |
Pathumthani |
| Owner
: |
MMC
Sittipol Co.,Ltd |
| Structural
Engineer : |
CASE
Co.,Ltd |
| Architect
: |
CASA
Co.,Ltd |
| Site
Area : |
40
Rais |
| Project
Cost : |
700
M.Baht |
| DesignCompleted
: |
January,
1995 |
| Structure
: |
The
complex composes of 4
low-rise buildings. Long-span
structures up to 50 metres
length are utilized. Pre-cast
concrete members are also
used to shorten the construction
time. |
|
|
| |
|
|
| Location
: |
King
Mongkut's Institute of
Technology (Thonburi),
Bangkhuntien |
| Owner
: |
King
Mongkut's Institute of
Technology (Thonburi) |
| Structural
Engineer : |
CASE
Co.,Ltd |
| Architect
: |
Burin
Srisook Architect Co.,Ltd
and Poomiwudht Co.,Ltd |
| DesignCompleted
: |
November,
1996 |
| Structure
: |
The
seven storeys building
will
be used for many functions.
The structural system
is beam column type with
precast
hollow core slab. The
basement will be used
as parking area which
cast-in-situ flat slab
is selected to prevent
water leaking and to reduce
uplift pressure. |
|
|
| |
|
|
| Location
: |
Thammasart
University, Pathumthani |
| Owner
: |
The
Ministry of Finance, Royal
Thai |
| Structural
Engineer : |
CASE
Co.,Ltd |
| Architect
: |
URDA
Co.,Ltd |
| Project
Cost : |
320
M.Baht |
| DesignCompleted
: |
1996 |
| Structure
: |
The
international zone consists
of
Ahlete Dining facility,
Recreation Center,Polyclinic
Fitness Center, Religious
Center and Major Office.After
the Asian Games,functions
are converted to the campus
community center, gymnasium,
kindergarten and school.
Due to the limitation
of construction period
concept of module structures
are utilized and pre-cast
concrete members are also
used to shorten the construction
time.
|
|
|
|
|
| Design Completed : |
January, 2002 |
| Owner
: |
Phuket Provincial Office |
| Structural
Engineer : |
CASE
Co.,Ltd |
| Architect
: |
East West Development Co.,Ltd. |
| Structure
: |
Located in Thalang, Phuket, the project composes
of many buildings in memorial for victory in
Thalang war. There are museum, library,
conference hall, office, restaurant, shopping area
and a miniature of Chaiya pagoda. |
|
|
| |
|
|
|
|
©
Copyright Civil and Structural Engineers Co.,Ltd.
All Rights Reserved. Designed by FortunerDesign
|
|
|
|
|